150 amp subpanel wire size
A 150 A subpanel feeder needs 1/0 AWG copper or 3/0 AWG aluminum at 75 °C, plus a ground. Detached garages and shops are often far enough away that voltage drop sets the size.
Feeder size
Fill in the circuit, then press the button.
150 A feeder
| Part | Copper | Aluminum |
|---|---|---|
| Hots and neutral | 1/0 AWG | 3/0 AWG |
| Equipment ground | 6 AWG | 4 AWG |
Table 310.16, 75 °C terminals, and Table 250.122.
A subpanel needs four wires: two hots, a neutral and a ground. In the subpanel the neutral bar is isolated from the enclosure and the ground bar is bonded to it. A detached building also needs its own grounding electrode (250.32).
Maximum distance at 3%, 120 A load, 240 V
| Copper | Ampacity | Max distance |
|---|---|---|
| 1/0 AWG | 150 A | 245 ft |
| 2/0 AWG | 175 A | 310 ft |
| 3/0 AWG | 200 A | 391 ft |
| 4/0 AWG | 230 A | 493 ft |
| Aluminum | Ampacity | Max distance |
|---|---|---|
| 3/0 AWG | 155 A | 238 ft |
| 4/0 AWG | 180 A | 300 ft |
| 250 kcmil | 205 A | 354 ft |
| 300 kcmil | 230 A | 424 ft |
Based on 80% of the breaker rating, a realistic heavy load. If the panel will see lighter use, 5% total is still within NEC guidance.
Common questions
What size wire for a 150 amp subpanel 100 feet away?
At 100 ft, 1 AWG copper or 1/0 AWG aluminum keeps the drop under 3% at 120 A.
What size wire for a 150 amp subpanel 200 feet away?
At 200 ft, 1/0 AWG copper or 3/0 AWG aluminum keeps the drop under 3% at 120 A.
Can I feed a subpanel with 3 wires?
Not for new work. Since the 2008 NEC, feeders to detached buildings need a separate equipment ground (250.32(B)).
Related calculators
Sources
- NFPA 70, National Electrical Code, 2023 edition (https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70)