200 amp subpanel wire size

A 200 A subpanel feeder needs 3/0 AWG copper or 250 kcmil aluminum at 75 °C, plus a ground. Detached garages and shops are often far enough away that voltage drop sets the size.

One way. Enter 0 to skip voltage drop.
V
%

Feeder size

Fill in the circuit, then press the button.

200 A feeder

PartCopperAluminum
Hots and neutral3/0 AWG250 kcmil
Equipment ground6 AWG4 AWG

Table 310.16, 75 °C terminals, and Table 250.122.

A subpanel needs four wires: two hots, a neutral and a ground. In the subpanel the neutral bar is isolated from the enclosure and the ground bar is bonded to it. A detached building also needs its own grounding electrode (250.32).

Maximum distance at 3%, 160 A load, 240 V

CopperAmpacityMax distance
3/0 AWG200 A293 ft
4/0 AWG230 A370 ft
250 kcmil255 A436 ft
300 kcmil285 A524 ft
AluminumAmpacityMax distance
250 kcmil205 A265 ft
300 kcmil230 A318 ft
350 kcmil250 A371 ft
400 kcmil270 A425 ft

Based on 80% of the breaker rating, a realistic heavy load. If the panel will see lighter use, 5% total is still within NEC guidance.

Common questions

What size wire for a 200 amp subpanel 100 feet away?

At 100 ft, 2/0 AWG copper or 4/0 AWG aluminum keeps the drop under 3% at 160 A.

What size wire for a 200 amp subpanel 200 feet away?

At 200 ft, 2/0 AWG copper or 4/0 AWG aluminum keeps the drop under 3% at 160 A.

Can I feed a subpanel with 3 wires?

Not for new work. Since the 2008 NEC, feeders to detached buildings need a separate equipment ground (250.32(B)).

Sources

  • NFPA 70, National Electrical Code, 2023 edition (https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70)